Verify Link actual to date and actual this period units and costs is selected.Ĩ.

#How to backdate a project in omniplan update
Verify Update units when costs change on resource assignments is not selected.Remove selection of Recalculate Actual Units and Cost when duration complete changes.Select the Add Actual to remaining option for When updating Actual Units and Costs.Select the Reset Planned Duration and Units to Remaining option is selected.Verify the Link Planned and At Complete for not started activities option is selected.Select the Activity percent complete based on activity steps option.Verify the Default Price / Unit for activities without resource or role Price / Unit is set to 0.00.Select the Calculations tab and complete it as follows: Verify the Total Float is less than or equal to is selected and the associated value is set to 0.0hħ.Verify the Baseline for earned value calculations is set to Project Baseline.You may have to change this again later, but 4 is usually a better starting point than the default of 2. Change the Summarize to WBS Level to 4.Select the Settings tab and complete it as follows: I’m going to assume the Calendar is set to something sensible.Ħ.Verify the Activity Type is set to Task Dependent, and change it if it isn’t.Change the Percent Complete Type is to Physical as it is most probably set to Duration.Verify the Duration Type is set to Fixed Duration & Units, and change it if it isn’t.Select the Defaults tab and complete it as follows: Click on the Status and set it to Planned.ĥ.I have set the Project Name to Newbie Project for which describes exactly what it is. Change the Project Name to describe what the project does.I have set the Project ID to NEWBIE in this example. Many organizations will tell you exactly what the Project Id will be. I would keep it to 8 capital characters or less. Change the Project ID to identify the project using a maximum of 20 characters.Select the General tab and complete it as follows: The bottom half of the screen should contain a set of tabs. The number at the end may be different.Ĥ. Take a look at your screen and you will see the highlighted project with a Project Id similar to NEWPROJ-1. If it is, click on the Finish button to exit the dialogue. The Create a New Project dialogue may be displayed. Create the new project by holding down the Control key and pressing the N key. Once you know which EPS Node to create the project, scroll down the list of EPS Node’s and Projects until you find it.Ĭlick on the EPS Node in the Projects Layout to select it.ģ. If you have been given access to someone else’s database then you will need to ask them where to create your project. If this is your own database then your project can be created under any EPS Node you want. Select the EPS Node where the project is to be created.Īll projects in P6 must belong to an EPS Node, which is a hierarchy intended to arrange projects in the way that makes the most sense for the organisation owning them. Believe it or not, there is no menu option to get there.Ģ.
#How to backdate a project in omniplan professional
I’m using Oracle Primavera P6 Professional Client v15.1 so if the Projects layout is not on my screen, I have to click on the projects icon on the left-hand side.
#How to backdate a project in omniplan how to
Also, that you are doing all this to learn how to use P6 for the first time.ġ. This post assumes you have the rights to create a project in P6 database you are attached to. Steps To Create A Project In Oracle Primavera P6 I make use of the Oracle Primavera Professional client throughout. The format of the post is a set of instructions for the newbie to complete and this is followed by some explanation. The detail and options available will be dealt with elsewhere. It is intentionally opinionated and prescriptive with the aim of getting the newbie user up and running as fast as possible.


This post covers how you create a project in P6.
#How to backdate a project in omniplan series
This is my first of a series of posts for new users of the Oracle Primavera Professional client.